The Transformation of the Carnegie Free Library of Allegheny into MuseumLab

MuseumLab lobby

What happens when you take a team of museum professionals, pair them with architects and contractors that have a shared interest in inspirational problem solving, and add shared commitment to discover and reinstate the historic architecture of a building that had been dampened by a 1970’s renovation?

You get MuseumLab – a special place at Children’s Museum of Pittsburgh where youth experience art, tech, and making.

How did it come to be?

“As we began the project of stripping back to reach a stable surface below crumbling plaster and column capitols that had been sliced through, we reached the building’s structural underpinnings. They were poetic and beautiful and a fitting backdrop for a program meant to look at how things are made. Our team embraced the idea of a beautiful ruin.”

Chris Cieslak, Sr. Director of Facilities & Special Projects, Children’s Museum of Pittsburgh.
Chris is now Chief Operating Officer for the Green Building Alliance.

History

In 2016, when Children’s Museum of Pittsburgh decided they wanted to reach a greater audience and needed more space to do so, they looked toward an adjacent empty and neglected building – The Carnegie Free Library of Allegheny – and turned it into an opportunity.

The Carnegie Free Library of Allegheny was built in 1890 with a generous donation from steel magnate and industrialist Andrew Carnegie. It was one of the first Carnegie free libraries in the United States and was nominated to the National Register of Historic Places in the 1970s. The City of Pittsburgh renovated the building in 1974, but in doing so, removed or simply covered the original interior ornamentation rather than undertaking a costly restoration.

By 2006, the library system was struggling with ongoing operating and maintenance costs. When a lighting bolt struck the building’s clock tower that September, causing a three-ton finial to fall through the slate roof and land upon a grand piano, the library moved out and the building sat vacant for a decade.

Project

“ Our green building efforts are an important part of the environment we create for our visitors as well as our community. Being LEED Gold certified confirms that we have done everything possible to nurture learning and inspire our guests in a facility that is highly sustainable.”

Jane Werner, Executive Director of Children’s Museum of Pittsburgh

The team from Children’s Museum of Pittsburgh, led by Executive Director Jane Werner, along with the talent and vision of Julie Eizenberg, Design Architect from  Koning Eizenberg Architecture, began to consider the possibilities of the empty building next door.

With a mission to provide innovative museum experiences that inspire joy, creativity, and curiosity and a vision to transform education, the Museum wanted to create a space for a big experiment where they could overlap formal education with a non-traditional learning environment.

They began assembling a team of partners to create MuseumLab with hopes of reestablishing the quality of the 52,000 square foot historic building that had been hidden by the 1970s renovation. In doing so, they embraced the idea of a “beautiful ruin.”

Beginning with a Sustainability Charrette and fully expecting to come out with a goal to pursue LEED certification, the team surprisingly discovered broader goals that tied back to the Children’s Museum’s vision of developing a more curious, connected, empathetic, and courageous citizenry. These goals included:

Challenges & Discoveries

The 18-month assignment to reincarnate the historic Carnegie Library building came with challenges as well as unexpected and beautiful discoveries and opportunities to restore, reuse and repurpose.

A colonnade was uncovered behind a bulkhead. The shadow of the original fireplace was revealed behind a carpet-covered wall. Light was reintroduced by restoring sealed exterior openings, and nooks and crannies to curate small oddities and artworks were created from holes left from the 1970s renovation.

A beautiful terracotta archway behind an existing wainscot was revealed from beneath layers of plaster on the last day of major construction, setting the team back two months in re-design. 

Achieving the 2030 District energy reduction goal was difficult. Replacing windows, roofing, mechanical systems, and lighting was not enough. The strategy needed to include insulation, but it came with a hefty price tag. 

It would cost $400,000 (four percent of the original $10 million budget) to insulate the walls with an eco-friendly thermal plaster made from pure natural hydraulic lime, cork, clay, diatomaceous earth, and reinforcing fibers that provided the necessary insulation while also preserving the building’s historic interior. Knowing it was the building’s one shot to get this right, the Children’s Museum Board President at the time, Mike Duckworth, wisely advised, “It is easier to raise funds for a GREAT building than it is for a good-enough building.”

With that encouragement and full support, MuseumLab went on to not only be the first museum in Pittsburgh to meet but to greatly exceed the 2030 District 50 percent energy reduction goal.

MuseumLab’s EUI (energy utilization index) went from 156 KBTUs per square foot (in 2003) to 57 KBTUs per square foot in 2019, the first year of MuseumLab’s operation – an 83 percent reduction.

Among its numerous awards and recognitions, MuseumLab is the proud recipient of the 2020 AIA Pittsburgh Silver Award based on its unusual approach to celebrating found architecture, the playful integration of artistic and functional elements, the resourcefulness and creativity of the project team, and the distinct ethos of the overall project.

Entry of MuseumLab. Photo © Eric Staudenmaier; Design Architects: KoningEizenberg; Architect of Record: PWWG.

“MuseumLab is one of GBA’s all-time favorite projects. The inspiring team created such a breathtakingly beautiful, magical, and creative space for the community while honoring the historic features and achieving the highest sustainability and health standards for renovation.”

Jenna Cramer, President & CEO, Green Building Alliance
MuseumLab main space

MuseumLab main space. Photo © Eric Staudenmaier MuseumLab. Overview by FreelandBuck. Design Architects: KoningEizenberg; Architect of Record: PWWG.

Project Team

Awards & Recognition

Sustainable Project Features

Related Articles

Design Pittsburgh 2020 Award Winners

A discovery at the Children’s Museum after tearing out plaster

Dezeen Awards 2020: Winners

MuseumLab: Expanding the potential for maker education in a lovely ruin

MuseumLab website

Top banner photo: Studio Lab of MuseumLab, looking into the Grable Gallery. © Eric Staudenmaier; Over View by FreelandBuck; Design Architects: KoningEizenberg; Architect of Record: PWWG.